# Hybar Order No. 2 — Original SRC Approval
The Commission's 8-page order approving the original Special Rate Contract between Entergy Arkansas and [[Hybar LLC]], a steel mini-mill in Osceola, Arkansas. **The most recent prior-art SRC approval in the APSC docket system before the [[psc/docket-23-025-p-hybar-2026-05-22/_overview|Altitude Capital / Google SRC]]**.
## Key takeaways
- The Commission finds the "proposed special rate contract between Hybar and EAL is in the public interest."
- Approval is contingent upon: (1) customer release from the City of Osceola to EAL (Hybar previously was within Osceola's municipal-utility footprint); (2) the Grant Agreement between Hybar and the City of Osceola to be filed in this Docket; (3) a request for customer release to be filed in a new docket.
- The Hybar SRC mechanism — a steel-mill customer relocation that requires a customer-release process from a municipal utility — is structurally different from Google's SRC (a new hyperscale data center on EAL territory from the start) but uses the same public-interest standard.
## Cross-references
See the [[psc/docket-23-025-p-hybar-2026-05-22/_overview|Docket 23-025-P production overview]] for context.